Bengalla_reconditioning_and_culvert_repairs_complete
Commercial Track Construction

Bengalla Reconditioning and Culvert Replacement

Rhomberg Sersa Australia (RSA) was engaged by ARTC to deliver the Bengalla Reconditioning and Culvert Replacement works. These projects were essential to improve track stability, enhance drainage performance, and extend the asset’s operational life.

“Scope was delivered in full and on time, site set up well, people/plant separation was good. Contractor went above and beyond, demonstrating strong initiative…positive and prompt communications and delivery of works.”
– ARTC Contractor Performance Report

Project Snapshot

Location
Bengalla, NSW
Construction period
November 2024
Client
ARTC
Executing companies
Rhomberg Sersa Australia

Scope of Works

Bengalla Junction Reconditioning – 291.540km to 291.730km

  • 190m of full track formation reconditioning to improve track resilience
  • Removal and reinstatement of existing rail and sleepers
  • Installation of new structural fill, capping, and ballast to ARTC standards
  • Cess drainage upgrades to manage water runoff and minimise maintenance
  • Rail welding and stress-free temperature adjustments to maintain track integrity
  • Track resurfacing and certification in line with ARTC requirements
  • Replacement of new Reinforced Concrete Box Culvert (RCBCs) 
     

Bengalla Junction Reconditioning – 291.540km to 291.730k

  • Complete replacement of the existing culvert to improve drainage capacity
  • Installation of new reinforced concrete pipes (RCPs) and headwalls
  • Excavation, proof rolling, and geotechnical treatment for a stable formation
  • Placement of capping and structural layers to protect the rail formation
  • Track reinstatement, resurfacing, and certification ensuring compliance with ARTC specification

Project Outcomes

  • Delivered on schedule during the November 2024 Major Possession
  • Optimised plant and resource allocation, ensuring efficiency and minimal delays
  • Integrated drainage solutions, reducing the risk of future maintenance issues
  • Collaboration with ARTC resurfacing teams, achieving high-quality track geometry
  • Improved track resilience and reduced maintenance requirements, enhancing long-term performance